SHAVER: Broad Project Plan

This is the large-scale project plan for the SHAVER project. Check back here for a summary of progress. The detailed project plan will be drawn up in consultation with project partners during February 2008.

Milestone date Description Progress
31st Jan 2008 Documentation of existing DEWS technology written and published In progress (delayed due to staff absence)
29th Feb 2008 Review of existing THREDDS and GeoServer code complete. Detailed project plan released In progress
31st May 2008 Early versions of modified THREDDS and GeoServer code complete and ready for test cases  
30th Jun 2008 Early version of GeoServer test case (with Earth System Atlas) complete *  
31st Jul 2008 Early version of THREDDS test case (with UK Met Office) complete *  
30th Sep 2008 Final versions of modified THREDDS and GeoServer complete and ready for testing  
30th Nov 2008 Both test cases complete and released  
31st Dec 2008 Project outcomes written up and published  

* The milestone dates for the two test cases have been switched because Adit will be away from July 18th to August 18th.

-- JonBlower - 01 Feb 2008