| Milestone date | Description | Progress |
|---|---|---|
| 31st Jan 2008 | Documentation of existing DEWS technology written and published | In progress (delayed due to staff absence) |
| 29th Feb 2008 | Review of existing THREDDS and GeoServer code complete. Detailed project plan released | In progress |
| 31st May 2008 | Early versions of modified THREDDS and GeoServer code complete and ready for test cases | |
| 30th Jun 2008 | Early version of GeoServer test case (with Earth System Atlas) complete * | |
| 31st Jul 2008 | Early version of THREDDS test case (with UK Met Office) complete * | |
| 30th Sep 2008 | Final versions of modified THREDDS and GeoServer complete and ready for testing | |
| 30th Nov 2008 | Both test cases complete and released | |
| 31st Dec 2008 | Project outcomes written up and published |